NIVOMAX Release Deployment Plan for Customer Distributions
Last Updated on July 26, 2024 | 5 min read
Estimated Timeline: 5 Weeks
Week 1: Planning and Preparation
Upgrade Release Kickoff
- Schedule a kickoff meeting with the client to discuss the scope, objectives, and timelines.
- Assign project roles and responsibilities.
Share Release Schedule and Plan
- Share the release schedule with the client, including dates, approval windows, and other relevant details.
Provide Release Documentation and Schedule Demo
- Collect detailed requirements and any specific customization needs from the client.
- Document any constraints or dependencies.
Perform Environment Review
- Review the client’s current environment and infrastructure.
- Identify any potential issues or upgrades needed to support the new software version.
Week 2-3: Preparing Distribution Release and Testing
UAT Form Preparation
- Create a UAT form to be submitted with the initial software release for the client.
- Ensure the form covers various test scenarios and expected outcomes.
Supporting and Help Content
- Prepare all related supporting and help content.
- Schedule and conduct a training session with the client’s SME teams to set expectations and demonstrate features.
Release Notes Document
- Produce a comprehensive release notes document detailing all new features, improvements, and bug fixes.
- Include screenshots or examples where necessary to clarify changes.
Perform Release Demo to SME
- Demonstrate the upgrade features to the client SMEs responsible for UAT and approval.
- Establish expectations, clarify constraints, and discuss workarounds if required.
Customer UAT Engagement
- Deploy the software to a UAT environment for the client.
- Encourage the client to test-drive the tools for real-life daily tasks to assess performance and familiarize themselves with the update.
Feedback Collection
- Gather detailed feedback from the client and document any issues or suggestions for improvement.
- Prioritize changes based on impact and feasibility.
Week 4: Evaluate Feedback and Pre-Production Preparation
Evaluate Feedback and Address Issues
- Internally evaluate feedback and address critical issues, if any.
Change Advisory Preparation
- Prepare the Change Advisory document for production deployment.
- Outline the planned changes, their impact on the system, and any associated risks.
Week 5: Deployment and Stabilization
Change Advisory Approval
- Obtain formal approval for the Change Advisory from all necessary parties.
Production Deployment
- Schedule and execute the production deployment.
- Follow established procedures to minimize downtime and disruption to the client’s operations.
Post-Deployment Stabilization
- Monitor the system closely for one week post-deployment.
- Identify and resolve any issues that may arise to ensure the update is stable and performs as expected.
Project Milestones
- Week 1: Release Kickoff
- Week 2-3: Preparation, Training, and UAT
- Week 4: Evaluate Feedback, Apply Changes, and Prepare Production Apps
- Week 5: Production Deployment and Stabilization Completed
Project Resources
- Delivery Supervisor: Oversees the release, ensuring timelines and deliverables are met.
- Development Team: Responsible for core software updates and customizations.
- Testing Team: Conducts internal testing and supports UAT.
- Client SME Teams: Engaged in training and UAT.
- Support Team: Provides ongoing support during the stabilization period.
Risk Management
- Risk: Potential delays in client feedback during UAT.
- Mitigation: Schedule regular check-ins with the client to ensure timely feedback.
- Risk: Issues discovered post-deployment.
- Mitigation: Have a rollback plan and a dedicated support team ready to address any critical issues.
This detailed project plan ensures a structured approach to upgrading and deploying the NIVOMAX software for the client’s customized distribution, with clear timelines, roles, and risk management strategies in place.
Sample Deployment and Upgrade Plan Template
Week | Task | Description | Start Date | End Date | Approval Responsibility | Notes |
---|---|---|---|---|---|---|
Week 1 | Upgrade Release Kickoff | Schedule a kickoff meeting with the client, discuss scope, objectives, timelines, and assign roles. | Delivery Supervisor | |||
Release Schedule Sharing | Share release schedule with the client, including dates, approval windows, and other relevant details. | Delivery Supervisor | ||||
Provide Release Documentation and Schedule Demo | Collect requirements and customization needs from the client, document constraints or dependencies. | Delivery Supervisor | ||||
Perform Environment Review | Review the client’s environment and infrastructure, identify potential issues or necessary upgrades. | Development Team | ||||
Week 2-3 | UAT Form Preparation | Create a UAT form for the initial software release, covering various test scenarios and expected outcomes. | Testing Team | |||
Supporting and Help Content | Prepare all related supporting and help content, conduct training sessions with client’s SME teams. | Support Team | ||||
Release Notes Document | Produce a comprehensive release notes document detailing all new features, improvements, and bug fixes. | Development Team | ||||
Perform Release Demo to SME | Demonstrate upgrade features to the client’s SMEs, establish expectations, and clarify constraints. | Delivery Supervisor | ||||
Customer UAT Engagement | Deploy software to a UAT environment, encourage client to test tools in real-life scenarios. | Client SME Teams | ||||
Feedback Collection | Gather detailed feedback from the client, document issues or suggestions, prioritize changes. | Delivery Supervisor | ||||
Week 4 | Evaluate Feedback and Address Issues | Internally evaluate feedback, address critical issues if any. | Development Team | |||
Change Advisory Preparation | Prepare Change Advisory document for production deployment, outline planned changes and risks. | Delivery Supervisor | ||||
Week 5 | Change Advisory Approval | Obtain formal approval for Change Advisory from all necessary parties. | Delivery Supervisor | |||
Production Deployment | Schedule and execute the production deployment, follow procedures to minimize downtime. | Delivery Supervisor, Development Team | ||||
Post-Deployment Stabilization | Monitor system closely for one week post-deployment, identify and resolve issues. | Support Team |